The contract works required are:
Classrooms
- Remove and dispose of carpet, supply and install of new 16oz direct carpet stick carpet tiles.
- Remove and dispose of the existing hessian wallcoverings. Supply and install new 10mm composite acoustic wall coverings.
- Existing exposed cables to be concealed behind the wall linings.
- Remove and dispose of the existing vinyl and replace with new.
- Supply and install lockable white board cabinets.
- Supply and install 2x interior sliding doors on adjoining walls between rooms 4 and 5 and rooms 2 and 3.
- Replace joinery with aluminium joinery and rebuild the existing brick windowsills as per the construction drawings.
Toilets
- Remove, dispose of the existing wall partitions and supply and replace with new.
- Remove, dispose of the existing pans and cisterns and replace with new.
- Remove, dispose of the existing vinyl and replace with new.
- Remove, dispose of the existing basins and replace with new.
- Replace joinery with aluminium joinery and rebuild the existing brick windowsills as per the construction drawings.
- Remove and replace the existing hot water and electrical supply.
Cloak Bay
- Remove and replace the existing vinyl as per the construction drawings
- Convert existing cloak bays to break out spaces.
Exterior
- Replace cladding as required around window joinery.
Project date: June 2023
Completion: October 2023
Total Project Value: $700,000