Project Scope – Refurbish interior of existing Administration Building, replace/refurbish the windows and re-roof the building in part. Construct new entrance canopy and
new external raised decking, stairs and ramps. Install specified structural components and building services systems. Complete associated external works.Demolish and dispose of two-classroom block with asbestos containing materials, as per MOE policies and procedures, and making good of neighbouring building.
Demolish and dispose of concrete walkways, ramps and steps.
Demolish and dispose of existing main entrance.
Demolish and dispose of internal walls, linings, ceilings and flooring.
Supply and install structural steel elements (posts and beams).
Remove and dispose of existing window and door joinery with new units to be supplied and installed.
Refurbish identified existing window joinery units.
Construction of new main entrance and external deck.
Construction of new walls and ceilings with insulation, linings, wall and floor coverings as well as paint.
Internal refurbishment of existing bathroom facilities and construction of new Acc. WC.
Limited exterior works remediating identified water egress issues.
Supply and installation of new joinery units for storage, reception and kitchen facility;
Installation of new and alternation of existing services including electrical, plumbing, fire and mechanical.
Siteworks including but not limited to landscaping, new asphalt area, new fencing and gates where detailed.
Richmond Road School
Home / Sectors /Â
Richmond Road School
Project start date: March 2020
Date of completion: April 2021 (This project was delayed due to Covid and the Council requesting it to become a total reclad)
Total Project Value: $1,933,000
Licenses & Certifications
Industry Verified Accreditations

Member of the certified Builders Association of New Zealand

Licensed Building Practitioner
Our Latest Creations
Latest Projects in Our Portfolio
Rise Up Academy
Rise Up Academy. Relocation of a classroom from Wiri to Mangere and refurbishment of a church[...]
Owairoa Primary School
Block 3 ILE Upgrade Block 3 currently comprises of 4 classrooms, and the girls/boys toilet blocks.[...]
Gulf Harbour Primary School
Bliss Reflexology
Kaurilands Primary School
Kaurilands Primary School Demolition of four classrooms. Construction of 3 MLE areas and refurbishment of 6[...]
Tamaki College
Tamaki College. Major refurbishment and rewiring of two story classroom block. Project Managers – APF Limited.[...]
Opaheke School
Project Scope – Opaheke School The current classroom block consisting of 4 classrooms is old[...]
Botany Downs Secondary College
This project involves the full refurbishment of the gym change rooms. Project Start Date: August[...]
Bright Sparks Early Childhood Centre
We are very excited to have won this job. It is the second project we will[...]
Chapel Downs Primary School
Project Scope – Library, Staffroom & Kitchen upgrade Demolition of old library, reception and ITC room.[...]