Sutton Park School

This school project consists of the major refurbishment of an old 6 classroom block. The work consists of a complete strip out including existing windows, doors, roof, electrics and flooring coverings etc. We are installing new roof trusses, windows, doors etc and then complete new interiors including heating, data, electrical and refurbishment of the existing…

Waimauku School

Contract Value – $550K. Architect – Fat Parrot Architecture. Project Manager – Quantum Meruit Ltd.    

Stanley Bay School

Stanley Bay School, consisted of four separate phases creating new teaching spaces. The works were carried out mainly during term times. Completed May 2015 Contract Value $350,000

Takanini School

[vc_row][vc_column width=”1/1″][vc_column_text]Takanini School Library. Project manager – Greenstone Group Ltd. Architect – Upton Architects Ltd. Contract Value – $277,000 This project consisted of the construction of an extension to the existing school library. The existing library is attached to the original 1920’s building. The school wanted the extension to appear to have  “Always been there”.…

Northern Auckland Kindergarten Association

Northern Auckland Kindergarten Association Construction of a new Kindergarten at Hobsonville Point, Auckland. Project Manager – Orion Projects Ltd. Architect – CASA Ltd Construction cost – $1,955,000 Construction commenced on this project in late February 2015 and is due for completion in August 2015. The architect, Phil Smith has designed the building with extensive use…

Pakaranga Heights Primary School.

Pakaranga Heights Primary School. Refurbishment of two teaching areas and construction of a covered verandah. July 2010 Value $50,000

Kindercare, Albany.

Kindercare, Albany. Extension to head officeCompleted April 2011 this work was carried out to the main office of Kindercare whilst the kindergarten below was operational.

Waterlea School, Mangere Bridge.

Waterlea School, Mangere Bridge. Refurbishment of two areas to make two IT suites. Construction of a covered verandah and accessibility ramp. Works were carried out whilst the school was open. Project manager – Carew Project Management Ltd. Value $100,000. July – August 2012

Sir Edmund Hillary Collegiate

Sir Edmund Hillary Collegiate. Refurbishment of two teaching blocks over four phases. Project consists of converting storage areas to a teaching space, conversion of a laboratory into a general teaching space, conversion of redundant toilets into new teaching spaces and refurbishment of laboratories. Project manager – Wallace Project Management ltd Value $435,000 August – December…

Kids Planet Albany

Kids Planet, Albany. Construction of a new two storey block consisting of teaching space and toilets to ground floor and Staffroom to first floor, Covered verandah and landscaping. Project manager – Orion Projects Ltd. Value $250,000 March – July 2013